Bid Number: 19-478-C
Bid Title: Airport Runway 14-32 and Taxiway Project
Category: Construction and Public Works (Chapter 149 and Chapter 30, 39m)
Status: Closed

Description:
Sealed Bids for Airport Improvements at Fitchburg Municipal Airport will be received at the Office of the Chief Procurement Officer, 166 Boulder Drive, Fitchburg, Massachusetts, 01420, on or before April 24, 2019 at 10:00 a.m. local time, at which time and place all Bids will be publicly opened and read aloud.  Bids submitted after this time will not be accepted. Bids must be submitted in a sealed envelope clearly marked “SHIFT, REALIGN, EXTEND, RECONSTRUCT, MARK, LIGHT AND SIGN RUNWAY 14-32 (APPROX. 5,000 LF X 100 FT) AND PARALLEL TAXIWAY (APPROX. 4,850 LF X 35 FT); CONSTRUCT STUB TAXIWAYS (APPROX. 240 LF X 35 FT EA); INSTALL PRECISION APPROACH PATH INDICATORS (PAPIS) ON RUWAY 14 AND RUNWAY 32; INSTALL RUNWAY END IDENTIFIER LIGHTS (REILS) ON RUNWAY 14 AND RUNWAY 32; AND CONSTRUCT NEW AIRFIELD ELECTRICAL VAULT, AIP 3-25-0018-028-2019, Bid Opening April 24, 2019, 10:00 a.m.”, along with the Bidders name and address.

This project will shift, realign, extend, reconstruct, mark, light, and sign Runway 14-32 (Approx. 5,000 LF X 100 FT) and parallel taxiway (Approx. 4,850 LF X 35 FT); Construct stub taxiways (Approx. 240 LF X 35 FT EA); Install precision approach path indicators (PAPIs) on Runway 14 and Runway 32; Install runway end identifier lights (REILs) on Runway 14 and Runway 32; and Construct new airfield electrical vault. Work on the Project will include: 

Construction of Runway 14-32 extended runway safety areas;
Shift, realign, extend, reconstruct, mark, light, and sign the new Runway 14-32;
Construct, mark, light, and sign the new parallel taxiways; 
Construct, mark, light, and sign the new stub Taxiways and;
Installation of NAVAIDs;
o Runways 14 and 32 PAPIs
o Runways 14 and 32 REILs
o Installation of new Runway 14-32 edge lights (MIRLs)
o Installation of new parallel taxiway and stub taxiway edge lights (MITLs)
o Installation of new airfield electrical vault
Installation of surface and subsurface stormwater drainage system; 
Installation of temporary and permanent erosion control measures;
Construction of wetland restoration areas;
Construction of other work as shown on the Plans, as specified in the Project Specifications and as directed by the Engineer.  

The Contract time for estimated construction completion is two hundred (200) calendar days.  The estimated construction cost for this project is $12,000,000.

PREBID MEETING TO BE HELD AT FITCHBURG AIRPORT

Publication Date/Time:
4/1/2019 2:00 PM
Closing Date/Time:
4/26/2019 10:00 AM
Submittal Information:
Bids due at 166 Boulder Drive, Fitchburg MA
Pre-bid Meeting:
04/09/2019 at 10:00 AM
Related Documents:
View Document(s)